A gas station lot can be a great site for a new building. It can also hide fuel in the soil and groundwater. Kee Enviro helps buyers, lenders, and owners find out what is there and what to do about it.
Who this page is for
- Buyers and developers of former stations. You want to buy a closed station or redevelop the land. You need to know what is in the ground and what cleanup could cost.
- Owners selling or refinancing. Your buyer or lender wants environmental reports. Current data helps you avoid surprises during the deal.
- Owners closing or upgrading tanks. You plan to take tanks out of service. Washington requires notice, a site assessment, and a report.
Building a new station is not the focus of this page. If you plan to buy land for a new station, get a baseline Phase I first. It records the site conditions before your fuel goes in.
Why these properties need extra care
Gas stations store fuel underground for many years. Tanks, piping, and dispensers can leak. EPA calls leaking underground storage tanks (USTs) “a common source of groundwater contamination.” Fuel can soak into soil, reach groundwater, and move off the property. EPA also says vapors can move into buildings, sewers, and utility corridors.
Removing the tanks does not end the risk. Contaminated soil and groundwater can stay after the tanks are gone. Many older stations also had service bays with waste oil tanks, lifts, and floor drains. Each one is another possible source.
Under Washington’s Model Toxics Control Act (MTCA), liability is strict, joint and several. A current owner can pay for cleanup even if a past owner caused the release. That is why you need the facts before you close.
What we test for
Washington’s cleanup rule sets minimum tests for petroleum releases in WAC 173-340-900, Table 830-1. We plan each Phase II around that table and the site history.
| Contaminant | Where it comes from | How we test |
|---|---|---|
| Gasoline and diesel range petroleum | Tank pits, product lines, dispensers, spills | Soil borings at each source, lab tests for petroleum ranges |
| Benzene and BTEX | Gasoline | Soil and groundwater samples |
| MTBE | Some gasoline blends | Groundwater with gasoline contamination, then soil if MTBE is found |
| EDB and EDC | Lead scavengers in older leaded gasoline | Volatile organics test of groundwater with gasoline, then soil if found |
| Lead | Old leaded gasoline | Soil tests for automotive gasoline releases before 1996, unless lead was not part of the release |
| PCBs and halogenated solvents | Waste oil tanks in old service bays | Soil and groundwater near the waste oil tank |
| Petroleum vapors | Fuel in soil or groundwater under a building | Soil vapor, sub-slab, or indoor air samples |
Washington rules that apply
Tank closure
Ecology’s UST program sets these steps for permanent closure of a regulated tank:
- Send Ecology a 30-day notice before closure work starts.
- Use ICC-certified UST service providers for decommissioning.
- Have a site assessment done by an ICC-certified site assessor, a Washington professional engineer, or a licensed hydrogeologist.
- Send the site assessment report within 30 days of closure if no release is found.
- Send a site characterization report within 90 days of closure if a release is found.
The owner or operator must report a suspected or confirmed release to Ecology within 24 hours.
Cleanup and No Further Action
Ecology’s Voluntary Cleanup Program (VCP) does not accept petroleum released from a petroleum storage tank system. These sites can use PLIA’s Technical Assistance Program (TAP) instead. PLIA is a separate agency, not part of Ecology. TAP reviews your reports and can issue a No Further Action opinion. PLIA says an NFA “may be helpful with property transfers.”
| PLIA TAP fee | Gasoline or diesel site |
|---|---|
| Enrollment | $10,000 per release or tank system |
| Periodic review, only if needed | $2,500 per release or tank system |
Contamination that did not come from a tank, such as a surface spill, may follow a different path. Ask Ecology early which program fits a site with both kinds of release.
Buying, selling, or refinancing
- Order a Phase I. Federal rules say it must be done within one year before you buy. Some parts must be done or updated within 180 days.
- Collect the tank records. Ask for tank closure reports, Ecology UST records, and any PLIA letters.
- Order a Phase II if needed. A former fuel use is often a recognized environmental condition. Testing gives you hard numbers.
- Price the cleanup. We estimate the scope so you can negotiate price, credits, or an escrow holdback. We send a written price for the Phase II scope.
If you own an active station, test before you list it. Data in hand lets you set the terms and keeps the buyer’s schedule on track.
Next step
Start with a Phase I Environmental Site Assessment. If you already know there is a concern, see our Phase II services or try the Phase II checker. Closing tanks? See our commercial UST closure service. Call Kee Enviro at 206-914-4989.